Internal access arterials, storm water network, heavy-duty hardstanding and utility corridors for an industrial growth centre, built to container axle loading.

Engineering Spec Sheet
payments
Contract Value
₹42.60 Cr
Item-rate contract
timer
Timeline Performance
On Time
20.0 months against 20 months
account_balance
Client Principal
SIPCOT Tamil Nadu
Industrial development authority
verified_user
Safety & QA Audit
0 LTI
510,000 field man-hours
Access Arterial
Access Arterial
Heavy-duty carriageway within the park
1 / 5
Section 03 // Detailed Engineering Dossier

Scope of Work & Structural Compliance

Industrial civil works delivered to IS code provisions for heavy loading, coordinated with the electrical, water and effluent packages.

01

Industrial Civils & PEB Erection

  • arrow_right_altHeavy Machinery Plinths:Reinforced plinths on isolated and raft foundations with vibration isolation dampers cast in.
  • arrow_right_altPre-Engineered Building Frames:Hot-rolled and cold-formed PEB frames erected and aligned to tolerance before cladding.
  • arrow_right_altAccess Arterials & Hardstanding:Internal roads and heavy-duty hardstanding designed for container and trailer axle loading.
  • arrow_right_altStorm Water & Utilities:Reinforced box drains, duct banks and utility corridors cast before the slab programme.
02

VDF Flooring & Utility Networks

Vacuum-dewatered flooring laid to FM2 tolerances, with embedded service trenches and effluent routing coordinated with process contractors.

Floor Tolerance
FM2
Vacuum dewatered
Frame Type
PEB
Pre-engineered building
Hardstanding
Heavy Duty
Container axle loading
Standards RegisterRev 2026
verified

Third-Party Independent Testing

Direct oversight and QA verification conducted by the Department of Civil Engineering, National Institute of Technology (NIT) Tiruchirappalli.

verified

Industrial Civil & PEB Code Compliance

Executed to the applicable Indian Roads Congress, MoRTH or RDSO specification for this class of work, with records available for departmental audit.

Concrete Compressive Strength Curve (M35 Grade)NABL Accredited
Day 7 — target 24.5 MPa26.8 MPa · 109.4%
Day 14 — target 31.5 MPa33.1 MPa · 105.1%
Day 28 — target 35.0 MPa39.2 MPa · 112.0%
Batch plant tested: 740 SamplesStandard deviation: ±1.5 MPa
Capital Plant Assets

Dedicated Machinery Fleet Mobilised

View full TTK equipment directoryarrow_forward
Asset: PAV-09Active

Vögele Super 1800-3

High-compaction tracked asphalt paver with AB 500 TV screed, capable of continuous 8.5 m paving widths with laser sensor grade control.

Paving rate
700 Tonnes / Hour
Asset: ROL-14Active

Hamm 311 Tandem Rollers

11-tonne heavy tandem vibratory compactors with integrated HCM asphalt compaction meters, used to guarantee 98% laboratory density.

Linear load
30.5 kg / cm Front
Asset: CRN-03Active

SANY 150T Crawler Crane

Heavy-duty lattice boom crawler crane mobilised for tandem lifting and millimetre-accurate placement of 72-tonne PSC bridge girders.

Lift capacity
150 Metric Tonnes
Asset: BPL-02Active

Schwing Stetter M1.25

Fully automated on-site concrete batching plant with aggregate moisture sensors, chilled water dispensing and computerised micro-dosing.

Batching rate
60 m³ / Hour
Construction Logistics

Execution Milestones & Phasing Velocity

Chronological phasing of the critical path operations for this contract.

Month 01

Park Layout Setting Out & Site Formation

Full setting out to SIPCOT layout drawings, with site clearance and formation across the arterial network.

Month 07

Storm Water Network & Utility Ducting

Box drains, catch pits and duct banks completed before road crust works to avoid repeat excavation.

Month 13

Road Crust & Heavy-Duty Hardstanding

GSB, WMM and bituminous courses laid across arterials, with concrete hardstanding for container parking.

Month 17

Kerb, Footpath & Signage Package

Kerbs, paver footpaths, signage and street lighting foundations completed across the internal network.

Month 20

Handover to SIPCOT

On Time

Joint inspection with SIPCOT engineers and formal handover of the internal infrastructure package.

format_quoteOfficial Client Endorsement

“The internal infrastructure was completed to programme and coordinated well with the other service packages. Drainage and ducting were finished ahead of the road crust, which saved us significant rework.”

Er. P. Rajendran

Project Engineer, SIPCOT Tamil Nadu

verifiedCompletion Certified
Cert No.SIPCOT/NLK/CC-2022/41
Signed & sealedNov 2022
Corridor Geometry

SIPCOT Industrial Park Alignment

map

Total corridor length: 12.60 KM

Nilakottai Entry Node to Growth Centre South Gate

Arterial Network
Internal roads and drains
Hardstanding
Heavy-duty container parking
Utilities
Duct banks and effluent routes
Tender Procurement & Joint Ventures