Status: Completed & Handed OverContract No. SR-MDU/ROB-719/2022 | Class 1 PWD Audited
Railway Infrastructure

Virudhunagar Junction – LC 380

Virudhunagar Composite Railway Overbridge (ROB LC-380)

Composite bowstring steel girder railway overbridge erected in synchronised night blocks under live overhead electric traction, eliminating level crossing LC-380.

Engineering Spec Sheet
payments
Contract Value
₹54.80 Cr
Railway works contract
timer
Timeline Performance
Zero Penalty
14.0 months against 14 months
account_balance
Client Principal
Southern Railway
With RVNL
verified_user
Safety & QA Audit
0 LTI
380,000 field man-hours
Composite Girder Span
Composite Girder Span
Bowstring girder over the running line
1 / 5
Section 03 // Detailed Engineering Dossier

Scope of Work & Structural Compliance

Executed to RDSO drawings and Southern Railway safety norms, with every erection stage cleared by the railway engineer before the line was reopened.

01

Rail Overbridge Substructure

  • arrow_right_altRail-Side Foundations:Pile and open foundations cast under railway supervision, clear of the running line and OHE masts.
  • arrow_right_altBox Pushing for Underbridges:Reinforced box sections pushed through live embankments on jacks within possession windows.
  • arrow_right_altPSC Girder Fabrication:Precast girders cast off-site to RDSO-approved drawings with certified tendon stressing records.
  • arrow_right_altApproach & Retaining Works:Reinforced earth walls and approach embankments built to railway formation standards.
02

Girder Launching Under Live Traction

Composite girder spans launched in synchronised night blocks under live overhead electric traction, with zero disruption to scheduled services.

Launch Method
Night Blocks
Speed restriction windows
Span Type
Composite Steel
Bowstring / plate girder
Clearance
OHE Compliant
Railway certified
Standards RegisterRev 2026
verified

Third-Party Independent Testing

Direct oversight and QA verification conducted by the Department of Civil Engineering, National Institute of Technology (NIT) Tiruchirappalli.

verified

Railway Civil Works Code Compliance

Executed to the applicable Indian Roads Congress, MoRTH or RDSO specification for this class of work, with records available for departmental audit.

Concrete Compressive Strength Curve (M50 Grade)NABL Accredited
Day 7 — target 35.0 MPa37.4 MPa · 106.9%
Day 14 — target 45.0 MPa47.1 MPa · 104.7%
Day 28 — target 50.0 MPa55.2 MPa · 110.4%
Batch plant tested: 620 SamplesStandard deviation: ±1.4 MPa
Capital Plant Assets

Dedicated Machinery Fleet Mobilised

View full TTK equipment directoryarrow_forward
Asset: PAV-09Active

Vögele Super 1800-3

High-compaction tracked asphalt paver with AB 500 TV screed, capable of continuous 8.5 m paving widths with laser sensor grade control.

Paving rate
700 Tonnes / Hour
Asset: ROL-14Active

Hamm 311 Tandem Rollers

11-tonne heavy tandem vibratory compactors with integrated HCM asphalt compaction meters, used to guarantee 98% laboratory density.

Linear load
30.5 kg / cm Front
Asset: CRN-03Active

SANY 150T Crawler Crane

Heavy-duty lattice boom crawler crane mobilised for tandem lifting and millimetre-accurate placement of 72-tonne PSC bridge girders.

Lift capacity
150 Metric Tonnes
Asset: BPL-02Active

Schwing Stetter M1.25

Fully automated on-site concrete batching plant with aggregate moisture sensors, chilled water dispensing and computerised micro-dosing.

Batching rate
60 m³ / Hour
Construction Logistics

Execution Milestones & Phasing Velocity

Chronological phasing of the critical path operations for this contract.

Month 01

Railway Boundary Survey & Safety Plan

Crane placement studies, block plans and OHE clearance drawings approved by the divisional engineer before mobilisation.

Month 05

Foundations & Piers Inside the Railway Boundary

Pile and open foundations cast clear of the running line and OHE masts, with continuous track monitoring.

Month 10

Steel Girder Fabrication & Trial Erection

Bowstring girders fabricated off-site, trial-assembled and dimension-checked before being moved to the block.

Month 13

Night-Block Girder Launching

Spans launched in synchronised traffic and power blocks under live traction, with the line restored each morning.

Month 14

Deck, Approach & Commissioning

Zero Penalty

Deck slab, approach roads and signage completed and the new bridge opened for road traffic over the railway.

format_quoteOfficial Client Endorsement

“The overbridge was erected entirely within the notified blocks, and the line was handed back on time after every possession. Documentation and safety compliance were maintained without exception.”

Er. S. Balakrishnan

Divisional Engineer, Southern Railway, Madurai Division

verifiedCompletion Certified
Cert No.SR/MDU/ROB/CC-2024/19
Signed & sealedFeb 2024
Corridor Geometry

Virudhunagar ROB Alignment

map

Total corridor length: 420 M

Virudhunagar Junction Approach to Bypass Link Road

Level Crossing
LC-380 eliminated
Girder Type
Composite Bowstring Steel
Erection
Night Traffic Blocks